The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Morogoro WSSA from 29.08.2022 to 01.09.2022.
The IFF - OBA team carried out a project monitoring visit on 18th August 2022. The team visited the ongoing construction works of 12.6km raising main DN600 diameter steel pipe and Pulsator Clarifier, rapid sand filter at Mowe treatment plant. During the visit the clear water storage tank was completed. The project is intended to increase the production capacity by 1,000m3/day through rehabilitation of water Treatment Plant and 12,000m3 through construction of new pulsator clarifier and two new rapid sand filters. The overall implementation including civil works and supply of material is at 67.5%.
The IFF Consultant conducted an interim visit from 15th – 17th June 2022. The aim of the visit was to assess the documentation of financial expenditure, to clarify some inconsistencies that occurred in the interim report. The team visited the rehabilitated storage tanks, domestic points, constructed 1.5km pipeline and interviewed newly connected customers. The total of 1,840 new customers have been connected. About 23,408 people will benefit from this project.
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Kahama WSSA from 05.06.2022 to 08.06.2022. The visit was aimed at the verification of output targets
The IFF OBA team, in cooperation with the representatives from Ministry of Water (MoW) and the Ministry of Finance and Planning (MOFP), carried out a project verification visit to the Singida WSSA from 23.05.2022 to 25.05.2022
From 9th to 10th of April 2022, the IFF-OBA team carried out a project proposal field assessment at the Shinyanga Water Supply and Sanitation Authority (Shinyanga WSSA). The utility submitted a project proposal to the IFF Secretariat that included the procurement of cesspit exhauster truck and extension of waste stabilization ponds
The IFF-OBA team carried out a project field assessment from 05th to 07th April 2022. The team visited the existing Iwambi treatment plant, the proposed site for the construction of storage tank and Kadete river.
The IFF OBA Consultant conducted an Interim visit from 22nd – 23rd February 2022. The aim of the visit was to assess the documentation of financial expenditure, to clarify some inconsistencies. The team visited the ongoing construction works of raising main, clear water tank and clarifier at the Mowe treatment plant. The project is intended to increase the production capacity of 1000m3/day.
The IFF Consultant conducted an Interim visit from 09th – 11th February 2022. The aim of the visit was to assess the documentation of financial expenditure and to clarify some inconsistencies. The team inspected the two procured exhauster trucks and visited the Busoka wastewater treatment plant.
The IFF - OBA team carried out a project monitoring visit on the 26th January, 2022. The team visited the Namfuo/Liti (control room and the equipped borehole), Kititimo well field (boreholes, collector tank and booster station) and the 200m3 Somoku storage tank. The connection of customers was on progress during the visit, with approximately 140 new customers connected out of 250 as an output target. Approximately 3,000 people will benefit from this project. The team also had the opportunity to visit the Automated Water Kiosks (ATM) and two different Prepaid smart water meters.
The IFF-OBA team carried out a project field assessment from 22nd to 24th September, 2021. The team visited the existing boreholes, storage tanks and booster station at Mtawanya, Mangamba treatment plant, Mbuo source (boreholes), Hiari storage tank and Mchuchu source where the water blending will take place. The team also visited Chiko/Lilungu disposal site.